PERFORMANCE REPORT


PERFORMANCE FOR THE MONTH OF MAY 2009

MONTHWISE PRODUCTION TARGET ON ECL
Performance for the month of May 2009

Parameters AAP Target  Actual % Achvd. AAP Target Actual L/Year % Growth
1. Coal Prodn. (M.Te)
UG 0.735 0.682 92.78 0.671 1.55
OC (D) 1.199 1.190 99.28 1.157 2.85
Total Departmental 1.934 1.872 96.81 1.829 2.37
OC(H) 0.424 0.392 100.91 0.359 6.50
Total Coal Production 2.358 2.264 96.02 2.253 0.50
2. O.M.S. (Te) 1.416 1.358 95.90 1.278 6.24
3. Despatch (M.Te) 2.320 2.510 108.18 2.354 6.61
4. O.B.R. (M.Cum.) 4.040 3.750 92.81 3.788 -1.00
5. Composite Prodn. (M.Cum)  5.437 5.684 104.54 5.283 7.59

PROGRESSIVE REPORT FOR MAY 2009

Parameters AAP Target  Actual % Achvd. AAP Target Actual L/Year % Growth
1. Coal Prodn. (M.Te)
UG 1.454 1.388 95.47 1.328 4.50
OC (D) 2.392 2.443 102.13 2.309 5.81
Total Departmental 3.846 3.381 99.61 3.637 5.33
OC(H) 0.803 0.775 96.50 0.783 -1.05
Total Coal Production 4.649 4.606 99.07 4.420 4.20
2. O.M.S. (Te) 1.369 1.351 98.74 1.265 6.79
3. Despatch (M.Te) 4.596 5.138 111.80 4.672 9.99
4. O.B.R. (M.Cum.) 7.942 7.869 99.08 7.619 3.29
5. Composite Prodn. (M.Cum) 11.057 10.955 99.08 10.580 3.55

In the month of May’09 ECL could  achieve 22.64 L.Tes against a target of 23.58 L.Tes. The main reason for shortfall in coal production was due to cyclone Aila from afternoon of 25.5.09 to morning of 26.5.09 accompanied by  high velocity wind and continuous heavy rainfall.  Due to this coal production particularly in opencast projects of all the operating areas including Rajmahal and SP Mines  was severely affected and most of the hired OC patches got waterlogged, production from which could not be normalized till now.

Production from underground mines also suffered due to disruption of power supply to many mines for long duration as due to cyclone Aila trees/electric poles were uprooted and overhead lines snapped atmany ny places.  Normal power supply was restored after 2/3 days.

Stock Liquidation:
Coal stock has been reduced from 2.52 MT (computed based on audited stock as on 1.4.08) as on 1.4.09 to 1.92 MT as on 31.5.09. Coal stock at Raniganj Coalfield reduced by about 0.26 MT and same at  Rajmahal reduced by about 0.24 MT

Profitability
During May’09, company made a loss of Rs. 49.12 crore against a loss of Rs. 2.69 crore during May’08. The Loss during April to May’09 was Rs. 73.97 crore against a loss of Rs. 38.38 crore during April to May’08.

Forestry clearance:
As advised by Dy. Conservator of Forest, Eastern Regional Office, Bhubaneswar, a presentation on Hurra ‘C’ project was made by ECL on 30.4.09 at Bhubaneswar. Further a team from Regional Office, Eastern Region, MOEF, Bhubaneswar inspected the site from 19.5.09 to 21.5.09. The application for clearance is expected to be forwarded to MOEF, New Delhi shortly.

Introduction of Continuous Miner at Sarpi UG mine:
For augmentation of UG production a contract has been signed with Joy Mining Machinery of UK for introduction of Continuous Miner at Sarpi UG mine. The equipment is expected to be delivered in October 2009. Equipment is scheduled to be commissioned in Dec 2009.